southern reservoir information

Southern Reservoir

image1

In 2019 Mt. View-Edgewood Water Company is constructing a 1 Million Gallon concrete reservoir.

Existing House Demolition

image2

A house next to the existing reservoirs was demolished to make room for the new reservoir.

Storm Water System

image3

Storm water piping has been installed to manage storm water runoff from the reservoir site.

Really Big Rock

image4

A very large boulder was found during the excavation for the reservoir foundation area.  It will be incorporated into the landscaping.

Reservoir Pad

image5

As of 5/28/19 the reservoir site has been excavated, base rock has been placed and compacted, and some underground utility installation is complete.

Reservoir Foundation

image6

On June 14 the concrete foundation and slab for the reservoir was poured.  The 12 recesses in the slab you see are for the concrete columns that will support the roof.

First Wall Section

image7

The contractor poured the concrete for the first section of wall on 7/19/19.  The contractor will pour five more sections over the next two weeks in July.

Second Wall Section

image8

Contractor poured the second wall section on Wednesday July 24.

Third Wall Section

image9

Contractor poured the third wall section on July 26.

4th and 5th Wall Sections

image10

Contractor poured the fourth wall section on July 30 and fifth wall section on August 1.

Reservoir Columns

image11

Between August 2nd and August 9th 11 columns and footings were poured.

Final Wall Section

image12

The last wall section and last column footing were poured on August 15th.  The last column was poured on August 16th.