southern reservoir information

Southern Reservoir

image64

In 2019 Mt. View-Edgewood Water Company is constructing a 1 Million Gallon concrete reservoir.

Existing House Demolition

image65

A house next to the existing reservoirs was demolished to make room for the new reservoir.

Storm Water System

image66

Storm water piping has been installed to manage storm water runoff from the reservoir site.

Really Big Rock

image67

A very large boulder was found during the excavation for the reservoir foundation area.  It will be incorporated into the landscaping.

Reservoir Pad

image68

As of 5/28/19 the reservoir site has been excavated, base rock has been placed and compacted, and some underground utility installation is complete.

Reservoir Foundation

image69

On June 14 the concrete foundation and slab for the reservoir was poured.  The 12 recesses in the slab you see are for the concrete columns that will support the roof.

First Wall Section

image70

The contractor poured the concrete for the first section of wall on 7/19/19.  The contractor will pour five more sections over the next two weeks in July.

Second Wall Section

image71

Contractor poured the second wall section on Wednesday July 24.

Third Wall Section

image72

Contractor poured the third wall section on July 26.

4th and 5th Wall Sections

image73

Contractor poured the fourth wall section on July 30 and fifth wall section on August 1.

Reservoir Columns

image74

Between August 2nd and August 9th 11 columns and footings were poured.

Final Wall Section

image75

The last wall section and last column footing were poured on August 15th.  The last column was poured on August 16th.  

Walls Completed

image76

Wall forms removed and reservoir with all the walls as of 8/23/19.

Interior Piping

image77

Interior steel piping for inlet, outlet, and overflow was installed in late August.

Roof Shoring

image78

Scaffolding and shoring installed in late August for roof placement.

Roof forming

image79

Forms for roof constructed in early September.  Rebar installation began 9/09/19.  Tendons were stressed on 9/6/19 and filled on 9/9/19.

Pouring Concrete Roof

image80

The concrete roof was poured on September 23, 2019.  Curing the roof and then removing the shoring will take several weeks.

Prepping Exterior Wall

image81

On 10/24 and 10/25 exterior wall was pressure washed to prepare wall for shotcreting.

10/28/19 Shotcreting video

Check out this video of the DN Tanks shotcreting the exterior of the reservoir on 10/28/19.

more southern reservoir stuff

Shotcreting Complete

image82

Contractor completed the shotcreting of the exterior walls on 11/14/19.

Horizontal Strand

image83

After the first layer of shotcrete was placed, seven-wire strand was wrapped around the reservoir on 11/1/19 and 11/4/19.

Shotcrete Cover Layer

image84

DN Tanks started with placing covering shotcrete layers on 11/06/19

MTVE 2019 Christmas Present

image85

Following the placement of the shotcrete, the walls were wrapped in plastic for water curing of the concrete on 11/15/19.

External Ladder Installed

image86

The roof access ladder was installed on 11/15/19.  The bottom is currently not attached because a couple feet of fill and a concrete pad will be installed later.