southern reservoir information

Southern Reservoir

image97

In 2019 Mt. View-Edgewood Water Company is constructing a 1 Million Gallon concrete reservoir.

Existing House Demolition

image98

A house next to the existing reservoirs was demolished to make room for the new reservoir.

Storm Water System

image99

Storm water piping has been installed to manage storm water runoff from the reservoir site.

Really Big Rock

image100

A very large boulder was found during the excavation for the reservoir foundation area.  It will be incorporated into the landscaping.

Reservoir Pad

image101

As of 5/28/19 the reservoir site has been excavated, base rock has been placed and compacted, and some underground utility installation is complete.

Reservoir Foundation

image102

On June 14 the concrete foundation and slab for the reservoir was poured.  The 12 recesses in the slab you see are for the concrete columns that will support the roof.

First Wall Section

image103

The contractor poured the concrete for the first section of wall on 7/19/19.  The contractor will pour five more sections over the next two weeks in July.

Second Wall Section

image104

Contractor poured the second wall section on Wednesday July 24.

Third Wall Section

image105

Contractor poured the third wall section on July 26.

4th and 5th Wall Sections

image106

Contractor poured the fourth wall section on July 30 and fifth wall section on August 1.

Reservoir Columns

image107

Between August 2nd and August 9th 11 columns and footings were poured.

Final Wall Section

image108

The last wall section and last column footing were poured on August 15th.  The last column was poured on August 16th.  

Walls Completed

image109

Wall forms removed and reservoir with all the walls as of 8/23/19.

Interior Piping

image110

Interior steel piping for inlet, outlet, and overflow was installed in late August.

Roof Shoring

image111

Scaffolding and shoring installed in late August for roof placement.

Roof forming

image112

Forms for roof constructed in early September.  Rebar installation began 9/09/19.  Tendons were stressed on 9/6/19 and filled on 9/9/19.

Pouring Concrete Roof

image113

The concrete roof was poured on September 23, 2019.  Curing the roof and then removing the shoring will take several weeks.

Prepping Exterior Wall

image114

On 10/24 and 10/25 exterior wall was pressure washed to prepare wall for shotcreting.

10/28/19 Shotcreting video

Check out this video of the DN Tanks shotcreting the exterior of the reservoir on 10/28/19.